why when i assign a role to a sub-task WeekPlan place a date on it?
When i start to plan a Task with Sub-Task most of the time i don't have still a date for them.
So i create both with Roles and Duration.
The problem is that wen i put a Role on a Sub-task the date field get today value.
I don't see any logic about that so i presume is a bug.
App:
Web app
Hi,
the sequence is:
Board section (tried in HIT same behaviour)
Create Parent Task then the sub-task
Put duration and Role ----> Today date sprouts!
I saw also that duration input is not compulsory, date is everytime created after Role is defined
It happens the same also in the windows app