Connection between High impact tasks in Goals and the Schedule

Avatar
  • updated
  • Answered

Hi,


Unsure whether this is a bug, or I've misunderstood how things are supposed to work.

In the Goals-page, I've created goals, and a set of high impact tasks related to these goals.

These high-impact tasks, shouldn't they show up in the Schedule-page, under the section Unscheduled high impact tasks? As is works now, I have to manually type in the high-impact tasks both in the Goals, and on the Schedule-page.


Thanks for helping out.   :)

App:
Web app

How would you rate the customer service you received?

Satisfaction mark by Dr Wong 6 years ago

Thanks for the quick and helpful reply with clear instructions.

Add a comment about quality of support you received (optional):

Avatar
Boo L.
  • Answered

Hi there,


Sorry to keep you waiting .


The High Impact task  you listed  will  not be visible in the Weekly Planner until you assign them to a date.


You may do this by clicking on" Edit Task"  or you can simply "Promote to today"





Assigning a date to the High Impact task will keep it showing in the High Impact task section as well as in the Weekly Planner section.

Let us know if there is anything else that we may assist you with.


Regards,
Boo
Avatar
Boo L.
  • Answered

Hi there,


Thank you for reaching out.  We are looking into your concern and we will get back to you as soon as we have more information.


Our apologies for the inconvenience.