0
Beantwoord

Why does an incomplete task's "task time" increase to 24hr when an incomplete task is automatically rolled over from one day to the next

ryan.a.burns 3 jaar geleden bijgewerkt door Aymeric (Founder) 3 jaar geleden 2
App:
GOED, IK BEN TEVREDEN
Satisfaction mark by ryan.a.burns 3 jaar geleden
Beantwoord

We have just deployed a fix for this!

I cannot see the zeroiing effect you are talking about. Do new estimates stay?